The
Environmental Protection Agency published its Final National Strategy to
Manage Post Construction Completion
Activities at Superfund Sites on Oct. 12, 2005.
According to EPA, the PCC Strategy has two main purposes: (1) to assure that
remedies put in place under the Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA or superfund) continue to protect human
health and the environment over the long-term; and (2) to focus EPAís efforts
during the next five years on activities to ensure human health and the
environment are protected at superfund sites after construction is complete.
At
first blush, these two purposes appear to be laudable and reasonable. Who would
argue against assuring the long-term protectiveness of superfund remedies?
Moreover, given the scope of liability associated with such sites, including
liability stemming from potential toxic tort claims, the agencyís focus on
long-term protectiveness would appear to coincide with the interests of
superfund responsible parties.
Unfortunately
however, given the breadth of its language, implementation of the post
construction completion strategy could have significant negative consequences
for the regulated community, most particularly the re-opening of remedies that
many have assumed were final. This could result in significant additional costs
and uncertainty for responsible parties. Worse yet, renewed focus on the long-term
nature of remedies could re-kindle dormant discussions regarding natural
resources damages. This article will describe the key features of the PCC
Strategy and analyze it from the perspective of a superfund responsible party.
The Superfund Cleanup Process
Most
companies are all too familiar with the process for remediating superfund
sites.
It begins with identification and listing of a site on the National Priorities
List, and continues with the study of the site, called the Remedial
Investigation, and the development of cleanup alternatives, called the
Feasibility Study.
Once the Remedial Investigation/Feasibility Study is complete, EPA selects the
remedy for the site, which is documented in the Record of Decision (ROD).
Underlying the decision on whether or not to require a remedy is a
determination of risks to human health, during the Risk Assessment, and the
environment, during the ecological risk assessment. Most Records of Decisions
identify both the selected Remedial Action and the long-term remedial goals.
Depending on the type of contamination associated with a site, the record may
identify cleanup goals for soils, sediments, groundwater, and surface water to
specified levels. The levels of cleanup are dictated by specified requirements
in other laws, referred
to as
ëëapplicable or relevant and appropriate requirements.íí
Implementation
of the Remedial Action typically occurs in three stages. First, the design of
the remedy, the Remedial Design, is completed. Second, the physical
construction of the remedy is performed. Finally, long-term care of the site
remedy is accomplished during periods
EPA
refers to as Long Term Response Action and Operation and Maintenance, which
includes operation of groundwater pump and treat systems, maintenance of landfill
caps, and long-term monitoring. CERCLA also dictates that sites be reviewed
every five years after physical construction of a remedy to assure, interalia, that the remedy remains protective. This is called
the Five-Year Review. Either during the Five-Year Review or otherwise, EPA will
employ what it calls Remedy Optimization, a phrase coined during a recent round
of superfund reforms. Remedy Optimization entails performing reviews to improve
the performance and/or reduce the costs of Long Term Response Action and
Operation and Maintenance. Generally speaking, those activities conducted
subsequent to remedy construction are called Post Construction Completion
activities.
Once
EPA is satisfied that no further response action is necessary, it can choose to
delete sites from the National Priorities List. Delisting sites from that list
is the ultimate goal of the superfund process.
The
study and remediation of a superfund site often can be even more complex than
described above. To be sure, the process is time consuming and extremely
expensive. Responsible parties, having invested considerable sums in a remedy,
often are loathe to consider additional remedy changes and attendant additional
costs. This is particularly true in large public companies in which internal
budgets and reserves may be in place based on current remedies. Many such
companies are involved in numerous sites, which compounds the issue.
Underlying Concerns
For
a variety of reasons, many sites will contain levels of contamination above
applicable or relevant and appropriate requirements for considerable periods of
time. For example, achieving specified cleanup levels, most typically in
groundwater, easily can take 20 to 30 years after completion of remedy
construction. In some cases, pump and treat remedies for groundwater, at least
in theory, can extend forever. Also, in certain situations, EPA may limit the
amount of physical cleanup necessary where achieving the specified applicable
or relevant and appropriate requirements is determined to be technically
infeasible. Finally, and more recently, EPA has recognized that the degree of
cleanup at a particular site, in both soils and groundwater, could be tailored
to the physical and environmental site setting, the expected long-term use of
the site, and the risks of future exposure posed by both the setting and future
use. In such instances, EPA may allow contamination to remain indefinitely.
This has been particularly true given EPAís recent emphasis on readying sites
for reuse for brownfields projects, a factor that may not have been considered
during the original remedy selection process. Regardless of the reason, many
superfund sites remain with levels of contamination above applicable or
relevant and appropriate requirements in both soils and groundwater after
remedy construction is complete.
Many
Records of Decisions, and in particular early Records of Decisions, do not
contain enforceable institutional control requirements to assure prevention of
exposure to contamination left in place over the long term. For example, while
EPA often times required that notices of the cleanup and the presence of the
contamination be placed in property deeds, actual restrictions on the use of
the property were not required. Examples of such restrictions, recorded with
the deeds for properties, include prohibitions on the use of groundwater and on
residential buildings.
Until
recently, EPAís activities under the superfund program have focused on the
completion of the Remedial Investigation/Feasibility Study, Remedial Design,
and physical construction of remedies. However, now that more than 60 percent
of superfund sites are through remedy construction, EPAís focus has shifted to
assuring long-term management of those remedies.
The post construction completion strategy sets out EPAís game plan to
accomplish long-term management and protection.
Legal Basis for the PCC Strategy
EPA
cites Section 121(b) of CERCLA as the legal basis for its PCC Strategy. This
section requires ëëa remedial action that is protective of human health and the
environment, that is cost effective, and that utilizes permanent solutions and
alternative treatment technologies or resource recovery technologies to the
maximum extent practicable.íí
It is clear from this language that
Congress intended superfund remedies to be permanently protective. During
remedy selection, EPA has gone about implementing this language through
application of nine criteria, set out in the National Oil and Hazardous
Substances Pollution Contingency Plan.
These criteria include: (1) overall protection of human health and the
environment, (2) compliance with applicable or relevant and appropriate
requirements, (3) long-term effectiveness and permanence, (4) reduction of
toxicity, mobility, or volume through treatment, (5) short-term effectiveness,
(6) implementability, (7) cost, (8) state acceptance and (9) community
acceptance.
Compliance
with each of the nine criteria is evaluated in different ways. For example, the
first two are ëëthreshold criteriaíí that all remedies must meet.
The third through seventh are ëëprimary balancing criteriaíí that are weighed
in various ways. The last two are ëëmodifying criteriaíí that are considered in
the final analysis.
While the initial selection of a remedy
by EPA relies on all nine criteria, the PCC Strategy appears to focus on the
first (overall protection) and third (long-term effectiveness) criteria, with
less emphasis on the others. EPAís emphasis on these two criteria, as well as
its reliance on the statutory language quoted above for its authority to
implement many aspects of the PCC Strategy, may be the subject of
challenges—particularly if EPA seeks to re-open remedies, require
financial assurance mechanisms for operation and maintenance activities
and
force implementation of institutional controls at many sites. Some may argue
that none of these activities are explicitly authorized by the statute.
The Post Construction Completion Strategy
The
PCC Strategy sets out five goals: (1) ensure remedies remain protective and
cost effective; (2) ensure institutional controls required as part of the
remedy are implemented and effective; (3) assure adequate financing and
capability to conduct post construction completion
activities;
(4) support appropriate reuse of sites while assuring remedy reliability; and
(5) improve site records management to better ensure remedy reliability.
EPA
describes the PCC Strategy as a ëëmanagement framework of goalsíí from which
ëërecommended approaches and initiativesíí will flow. The approaches and
initiatives are targeted at fulfilling each of the five enumerated goals. The
PCC Strategy cites to a number of pre-existing guidance documents, many of
which were developed during superfund reforms in 2004. Based on the broad
language of the PCC Strategy, EPA intends to evaluate all construction complete
sites against these goals. To the extent that EPA deems that a remedy needs to
be changed, it intends to re-open Records of Decisions.
The
remainder of the PCC Strategy discusses how EPA anticipates achieving each
goal. Interestingly, EPAís approach involves initiatives aimed at ëëoptimizing
remedies to increase effectiveness and/or reduce cost without sacrificing
long-term protection of human health and the environment.íí A close reading of
this ëëoptimizationíí approach reveals a number of new requirements that EPA
may impose on responsible parties at sites. In other words, in the context of
ëëachieving goalsíí and ëëoptimizing remedies,íí EPA proposes to implement a
variety of new initiatives that will impose new requirements on those
responsible for completion and maintenance of remedies. To understand the
potential for responsible party impacts, further discussion of each goal and
the proposed initiatives is necessary. For a variety of reasons, it is safe to
assume any additional costs associated with implementation of the PCC Strategy
will be borne by the responsible parties.
Goal
1—Ensure that remedies remain protective and cost-effective. EPA explains that there are a number of tasks
involved in ensuring remedies remain protective and cost-effective. For
example, O&M of engineered remedies (e.g., containment, pump and treat, and
ongoing soil remedies) is necessary over the long term. This involves
monitoring, repair, and replacement of existing structures as necessary to keep
the remedy in place and functioning. Also, EPA notes that large volumes of data
must be managed to track progress. Tracking progress could result in
implementing operational changes.
Interestingly however, EPAís discussion
of this goal goes beyond merely implementing operation and maintenance and
operational changes to existing remedies. For example, EPA states that initial
remedies are ëëselected, designed, and constructed based on the best knowledge
of site conditions and technology available
at the timeíí and ëëmost remedies
will have a dynamic nature over time.íí
This language suggests that ensuring protectiveness may likely entail wholesale
reconsideration of fundamental aspects of remedies.
EPA
cites several assessment factors that could cause it to reevaluate existing
remedies, including changing site characteristics and technological innovation.
Presumably, therefore, EPA could determine that a remedy needs to be re-opened
either because a new and better technology has been developed or because the
area surrounding the site has changed. Perhaps most telling is
EPAís
statement that ëë[r]emedy update types could include not only changes in the
remediation technology, but also modification of the remediation objectives."
To accomplish this goal, the PCC Strategy recommends better tracking of
remedies by EPA, development of ëëEnvironmental Management Systemsíí approaches
(e.g., plan, review, and improve), and modification of enforcement documents to
include provisions aimed at assuring long-term goals (e.g., financial assurance
provisions).
Goal
2—Ensure that institutional controls required as part of the remedy are
implemented and effective. Institutional
controls (ICs) are administrative, legal
controls that minimize exposure
to remaining contamination and
protect the integrity of remedies. Examples include deed restrictions on land use and groundwater. EPA
recognizes that its past assumptions
regarding institutional controls
may not be correct. For example, EPA has recognized that implementing, monitoring, and enforcing institutional controls at sites is considerably
more complicated than previously
understood. Therefore, the
agency intends to revisit institutional controls to ensure long-term protectiveness of remedies.
It
also appears that EPAís concerns go beyond currently implemented institutional controls. Many sites at
which remedy construction is complete have
no deed restrictions in place.
Therefore, a necessary prerequisite to achieve the second goal is to require implementation of institutional controls in the first place.
EPA
has been assessing institutional controls at sites for several years and has published several guidance
documents on the subject.
In fact, EPA recently completed an initial
round of institutional controls data entry into a database of sites at which construction is
complete. Those efforts are
ongoing.
Part
of EPAís assessment of institutional controls involves targeted information requests to responsible
parties. Recently, EPA sent out
such information requests regarding
the use and enforceability of institutional controls at particular sites. Responsible parties
that have not yet received such
a request, are likely to in the relatively
near future. These requests are very broad and require the submission of documents, including a
legal opinion on the enforceability of
institutional controls. A
legitimate question exists as to the legal authority of EPA to request such information.
The
language of the post construction completion strategy, as well as recent
experience, appears to strongly suggest EPA will require institutional controls
at all sites where residual contamination remains in place after remedy
completion. Unfortunately however, there are situations in which the landowner
may not be readily identifiable or approachable (due to death, bankruptcy,
complicated corporate restructuring, etc.). In these instances, neither the
responsible party nor EPA may have the legal authority to impose deed
restrictions.
Ironically, implementation of this goal
may impede EPAís ability or willingness to delete sites from the National
Priorities List. At one such site, an old unlicensed landfill, EPA has decided
institutional controls, which were not part of the original remedy requirement,
must be in place prior to site deletion. By EPAís accounts, the remedy has been
extremely successful, and the site is touted by EPA as a success story. As a
result, EPA approached the responsible parties about deleting the site from the
National Priorities List. However, after reviewing the case EPA determined that
a deed restriction needed to be in place prior to site deletion. Because this
is a site at which ownership remains unclear, it may be impossible to implement
a deed restriction. EPA is therefore delaying site deletion. Clearly attaining
Goal Two may involve considerable effort on the part of EPA and responsible
parties. In some cases, it may be impossible
to
achieve this goal.
Goal
3—Assure adequate financing and capability to conduct post construction
completion activities. The development
of this goal is rooted in EPAís
recognition that assuring long-term
activities at superfund sites likely will cost a considerable amount of money. Unfortunately, EPA believes it has no statutory authority to fund
any such work, except in certain
circumstances. For example, EPA explains that it cannot utilize superfund
money to fund any work beyond Long-Term
Response Action (e.g., 10 years
of pump and treat).
Whether or not the statute actually
supports this conclusion, it appears EPA will require others to assume the costs of such long-term activities.
The
PCC Strategy states that superfund relies principally on state governments and responsible parties to
ensure long-term operation and maintenance
is performed at sites. However,
EPA correctly identifies two key
limitations of this approach. First, states have fewer dollars to spend on superfund sites and, therefore,
have a very limited capability
to oversee operations and maintenance,
let alone to conduct it themselves. Second, as more sites enter the post construction completion
cleanup phase, overall costs are likely to
rise significantly. The PCC
Strategy states that EPA and the states
are in the initial stages of identifying the ëëfull complement of funding mechanisms for financing
sites.íí
Short
of new state or congressional funding for such work, which seems unlikely, it
appears obvious that the costs for such work are likely to be borne by
responsible parties. In fact, the PCC Strategy recommends that EPA and others
work to ensure that responsible parties fulfill their operation and maintenance
obligations. This effort will involve the implementation of financial assurance
mechanisms similar to those required for RCRA Corrective Action cleanups
(bonds, letters of credit, etc.). Whether EPA has the legal authority to insist
on such financial assurance is an issue. Furthermore, it is unclear how EPA
will seek to impose such requirements, particularly in cases in which
settlements were finalized many years ago.
The
likely fact that the costs of operation and maintenance will be visited on
responsible parties should not come as a surprise. Responsible parties have
long recognized that superfund liability is forever. The real question is
whether such costs ultimately will be more expensive because of the application
of the PCC Strategy. In addition to the potential costs associated with
remedy
revisions, the costs associated with purchasing and maintaining a financial
instrument to assure 30-plus year operation and maintenance programs (e.g.,
pump & treat systems) may be significant. Also, costs to fund state
oversight programs likely will be added to the responsible partyís tab.
Goal
4—Support appropriate reuse of sites while assuring remedy reliability. This goal fits well with EPA and various state
efforts to encourage the reuse of superfund sites under the rubric of both
federal and state brownfields programs. Through implementation of this goal,
EPA seeks to speed up the process of providing approvals for redevelopment of
superfund sites. The PCC Strategy states that a site need not be deleted from
the National Priorities List before being deemed ëëready for reuse.íí Rather,
sites may be so designated once remedy construction is complete and necessary
controls on residual contamination are in place. Under a new initiative, called
ëëReturn to Use,íí EPA will review sites for ways to reduce actual or perceived
barriers to
redevelopment.
In some cases, and as discussed previously, this may involve changes to the
remedy in the form of an amendment to a Record of Decision or an Explanation of
Significant Difference (used in situations where the remedy is modified but not
fundamentally changed).
Goal
4 is very significant for redevelopment projects. Unfortunately, the PCC
Strategy contains little specific detail on how EPA will determine sites are
ready for redevelopment
or on
what conditions will preclude such a determination. Presumably the details are
to be worked out on a site-specific basis.
Goal
4 is something to applaud in theory. However, in practice there may be some
very significant issues for responsible parties that are left unaddressed,
particularly in terms of residual liability after reuse is accomplished. For
example, a responsible party may have no control over the property at the time
reuse is contemplated. Perhaps it never owned the property or may have sold it
years ago. Therefore, it may be unable to contractually assure that its future
liability is covered. Moreover, the new owners/redevelopers generally negotiate
some form of liability relief with EPA or the state. Regardless of their
ability to deal with their liabilities contractually, some responsible parties
may legitimately feel that they have nothing to gain, and everything to lose,
by redeveloping former properties. This issue is left unaddressed by the PCC
Strategy.
Consider a scenario in which a developer
purchases a former industrial property containing residual contamination. The
developer, which acquires title to the property via a limited liability
corporation, then develops the property utilizing engineered structures (caps/
barriers/etc.) to prevent ongoing exposure to contamination. As part of an
agreement with EPA or the state, the developer agrees to maintain those
structures.
The
development may be a great success and draw additional development, along with
additional population, closer to or even onto the property. What if that
developer is suddenly out of the picture? Perhaps its other projects were not
as successful and it goes bankrupt? In any event, what remains is a responsible
partyís worst fear—additional potentially exposed populations and
engineering controls that may be very expensive to maintain. Who is left
holding the bag in this scenario? Certainly not the government. The developer
is gone. The only one left is the responsible party, for whom liability is
forever.
Goal
4 does little to protect even the current liability status of the responsible
party. In fact, it may create a situation in which the responsible party is
left in a worse position. Goal 4 does not, for example, seek to require the
developer to provide financial assurance for the operation and maintenance work
its development has created. Also, goal 4 does little to incentivise a responsible
party that currently owns properties to release them into the brownfields
marketplace. While certain mechanisms are available, such as environmental
insurance products, to insure certain risks associated with redevelopment, goal
4 does not seek to impose them as a condition to redevelopment. Goal 4 should
be further developed to deal with such issues and to provide meaningful
protections and incentives for moving forward with brownfields projects.
Goal
5—Improve site records management to better ensure remedy reliability. This goal is aimed principally at upgrading EPAís records management procedures. It
seeks to ensure data about site conditions
and cleanups, including required
institutional controls, will be available when and if needed in the future.
While
responsible parties have no direct obligation for implementing goal 5, they should nevertheless consider implementing comparable records management
systems to protect their long-term
interests. For example, records
related to historical site conditions and chemical use, present site conditions including constituents present, and cleanup activities conducted, should
be maintained and be accessible. Such
information may be critically
important in 20 years to defend a toxic tort suit by showing the contaminants of concern were
released at the site after the
responsible partyís tenure at the
property.
While
many large companies have sophisticated records management systems in place,
most focus on ongoing
operational records. Some do not encompass historical records, particularly historical records
relating to formerly owned or
operated facilities. Records management
systems should be reviewed and revised in order to capture this type of information.
Summary of Responsible Party Concerns
Clearly,
the PCC Strategy raises a number of concerns for responsible parties. Much of
the language of the strategy is extremely broad. The specter of wholesale
remedy revisions is of great concern. However, the notion of even more modest
remedy revisions raises similar concerns. Most companies, particularly large
ones, have done fairly well managing superfund liability over the years. Many
of them are under the impression that sites at which remedial construction is
complete are under control and are accounted for from a financial perspective.
Even modest changes at multiple sites may prove those assumptions wrong.
Putting
aside actual remedy changes, companies with large numbers of sites will have to
review and manage the post construction completion process for their sites.
Responding to EPA queries regarding institutional controls, implementing
institutional controls, conducting technical reviews of existing remedies
against new technology and changing patterns of population movement, and
implementing requirements to comply with new financial assurance provisions
will require significant efforts.
In
addition, the fact that EPA may be required to transition many of these sites
to state agencies likely will raise additional concerns. States that do not
have the budgets to oversee these sites will seek to impose those costs on the
responsible parties. Some companies also are concerned that states may be more
inclined to revisit remedies. This may simply be a function of having new sets
of eyes review projects. Also, many states have implemented new cleanup
policies and requirements since the original remedy was selected at a given
site. Some of these may be more stringent than federal requirements and more
stringent than those in place at the time EPA selected the remedy. Examples
include vapor intrusion policies, more stringent cleanup levels, more stringent
wetlands requirements, and more stringent air and water discharge limits,
including those resulting from Total Maximum Daily Loads that could affect
groundwater treatment systems. States may feel that they must impose these new
requirements at sites now under their direct control.
Perhaps
the most alarming consideration is the possibility that renewed focus on the
long-term nature of some cleanups (e.g., a 30-year pump and treat remedy) may
create a higher likelihood that states will bring natural resources damages
claims against responsible parties. Several states already have been active in
bringing natural resources damages claims. Such claims have the potential to be
significant.
Conclusion
It
is perhaps inevitable that post construction issuesare squarely on the table at
this time in superfundís history. As EPA notes in the PCC Strategy, the program
is maturing to the point where the majority of sites are in the post
construction phase. For most of these sites, remedy selection occurred many
years ago and there are a variety of new remedial technologies available.
Moreover, critical thinking about how best to manage sites and to conduct
cleanups has evolved significantly. In addition, EPA and state policies
encouraging redevelopment, as well as developersí willingness to redevelop
sites, are changing fundamental assumptions about long-term use of certain
properties. In fact, the post construction completion strategy squarely raises
the specter that no remedy is ever final. As discussed, EPAís approach to
managing such sites may well result in re-opened remedies, requirements for
financial assurance mechanisms, implementation of institutional controls,
additional federal and state oversight costs, and the possibility for renewed
focus on natural resources damages. Viewed in this light, EPAís PCC Strategy
raises significant financial concerns for responsible parties.
Whether
or not the implementation of the PCC Strategy will result in significant new
costs, responsible parties should not ignore the process. It certainly makes
sense for companies to oversee, manage, and address all relevant issues at post
construction complete sites. Moreover, responsible parties must become involved
in the process to assure that implementation of the post construction
completion strategy does not result in superfund redux.